Gawar Wins Delhi – Katra Expressway’s Package 18 in J&K

TNN Bureau. Updated: 3/18/2023 12:28:16 PM Business and Economy

NEW DELHI: Gawar Construction Ltd. on Friday was declared as the lowest bidder for the civil contract of 650 km Delhi - Amritsar - Katra (DAK) Expressway‘s 15.3 km Package 18 in Jammu & Kashmir.
This 4 lane (expandable to 8) greenfield project by National Highway Authority of India (NHAI) consists of 2 phases. Phase 1 consists of 12 packages for the 397.71 km Delhi - Gurdaspur section and 3 packages for the 99 km Nakodar - Amritsar spur.
Package 18 in Jammu & Kashmir is part of Phase 2 (mostly brownfield upgrade) connecting Gurdaspur - Pathankot - Jammu - Katra. This package involves upgrading the existing national highway NH-44 north of Jammu city between Sidhra and Ban villages into an access-controlled roadway.
The project's Detailed Project Report (DPR) was prepared by Feedback Infra, and NHAI invited bids for its construction in December 2022 under the Hybrid Annuity Model (HAM) model with a 730 day (2 year) deadline and a Rs. 777.56 crore estimate.
Technical bids were opened in mid-February to reveal 5 bidders.
Financial Bid Values
Firm Bid (Rs. Crore)
Gawar Construction Ltd. 650.99
Ram Kumar Contractor Pvt. Ltd. 691.85
Vijay M Mistry Construction Pvt. Ltd. 734.79
APCO Infratech Pvt. Ltd. 762.23
Ceigall India Ltd. 837.00

Brief Scope: Development and Upgradation of Four lane Access Control Expressway from Design Chainage Km 530.000 to Km 545.300 (Sidhra to Ban Village Section of NH-44) of Delhi Amritsar Katra Expressway on EPC Mode under BMP in the UT of JK (Phase II-PKG-XVIII)

Gawar's bid of Rs. 650.99 crore was well below NHAI's estimate of Rs. 777.56 crore so a contract should be awarded in the coming weeks. On the greenfield section (Phase 1), a tender notice for Package 13's construction near Gurdaspur is still pending. A complete list of Delhi - Katra Expressway's civil packages and their contractors.