Guv reviews tunnel projects, BVR to take monthly review

TNN Bureau. Updated: 8/19/2018 11:26:50 AM Front Page

SRINAGAR: The Governor NN Vohra on Saturday took a review meeting of certain major road projects being executed by the National Highways and Infrastructure Development Corporation Limited, notably the pace of execution of the vital Z Morh and Zojila Tunnel projects.

Nagendra Nath Sinha, Managing Director, NHIDCL made a presentation to inform that under the Z Morh Tunnel Project, 42 % of the physical progress had been achieved in the case of excavation works and of the targeted 13,000 m of excavation 5,489 m has been completed and a Ventilation Tunnel of 596metre length had been completed.
Pertinently, the work on Z Morh Tunnel, with a total length of 6.5 km alongwith its approaches, is being constructed between the villages of Rezan and Shetkari on the Srinagar - Leh Highway. It is planned tobe completed in April 2020.
Governor also reviewed the progress of Zojila Tunnel which will provide all weather year round connectivity between Srinagar, Kargil and Leh. It was informed that Zojila Tunnel will reduce the travel time from 3 hrs to 15 minutes. Work on this tunnel, started in May 2018, is expected to be completed in May 2025.
Governor discussed in detail the proposed ventilation and other facilities in both these tunnels and directed Dr. Piyush Singla, Deputy Commissioner Ganderbal, to immediately finalise location for setting up Medical facilities with CCU and positioning of Specialists, especially for coronary care and high altitude ailments. He directed Chief Engineer PDD to urgently prepare DPR for providing uninterrupted 3X 10 MVA power supply for work in both the Tunnels.
The meeting also reviewed the construction of Approach Road to the Western Portal of the Zojila Tunnel. Sinha informed that a detailed study is being conducted along with the Snow and Avalanches Study Establishment for construction of this 20 km stretch which has approximately 30 avalanche prone sites and the work has already been awarded.
While reviewing the status of four laning of the Jammu-Akhnoor National Highway, Governor asked Advisor Khurshid Ahmed Ganai to visit the sites which are facing issues relating to alignments, widening, shifting of utilities, land acquistion etc. and decide the same on the spot, as possible.
Governor directed Shahid Anayatullah, Commissioner Revenue and Saurabh Bhagat, Commissioner Forests, to ensure urgent resolution of issues relating to Land Acquisition, Forest clearance and Tree Fellings.
Governor also reviewed physical progress of the proposed Alternate Highway on Chenani – Sudhmahadev – Goha – Khellani – Kishtwar – Sinthan Pass – Khanabal section of NH-244 and directed early completion of land acquisition and forest clearances. Sinha, informed that roads from Chatrooto Sinthantop (60 % completed) and Sinthan Top to Khanabal (30 % completed) are being improved through regular maintenance.
Governor asked BVR Subrahmanyam, Chief Secretary to take an early meeting to settle all issues regarding the provision of security cover to the entire staff engaged in the Tunnel Projects and settle related matters with the Ministry of Home Affairs. Governor desired CS to take monthly meetings to review the two Tunnels and the projects discussed in today’s meeting and ensure against any delays holding up the pace of works.